Description of works

Membrane Installation
Scaffolding design and fabrication
Provision of project resources
Acheiving productivity demands
   
Project Period  
  Sept 2002 - Nov 2003 
       
Project Details

Works on the tunnel were over two sites, with membrane installation totalling 400,000m2. Considering the scale of the works, EPTEC was required to devise methods of installation, designing a scaffolding structure that would enable the applicators of the membrane to access the tunnel profile with easy mobility.

EPTEC provided expert labour and supervision establishing itself as an industry leader, while using material that exceeded benchmark specifications.

EPTEC resourced the entire project using both local and international suppliers, maintaining a working liaison with the client to meet critical project demands.
 