<< Back to Case History

End User/Client
 
  Transfield Obayashi Joint Venture /Transurban
   
Location
  Melbourne, Australia
 

Description of works

Chemical grout injection
Material and method selection
Inspection and testing
     
Project Period  
  June 1999 - Dec 1999
   
Project Details      

Planning and engineering of the infiltration control system was completed in liaison between EPTEC, the Client and Consultants prior to commencement of work. High in-flows and water pressures required special materials and techniques to achieve successful completion.

EPTEC completed the work on time and the tunnel was successfully opened for traffic. The successful completion and reputation generated by EPTEC in this tunnel led to further work on the Burnley Tunnel the following year.
 

 
 


 

 
 
 
 
 
 
 
 
 
<< back to case history | top