End User/Client
  Thiess Hochtief JV NSW State Rail
   
Location
 

Sydney West

 

Description of works

Liquid waterproof membrane spray applied to four station caverns
Chemical Injection waterproofing in running tunnels and station caverns
   
Project Period  
  2004 - 2006
     
Project Details  

The Epping to Chatswood section of the Parramatta Rail Link is an underground train-line being built to service Sydney's Northwest. The stations are situated at Macquarie University, Macquarie Park and Delhi Rd.

.The underground station caverns required water-proofing to prevent the ingress of ground water. Eptec pressure injected chemical waterproofing material to many areas in the station caverns and running tunnels. Eptec spray applied liquid membrane to approximately 25,000sqm to a dry film thickness of 3mm, spraying in allotments ranging from 500sqm to 2500sqm. A direct benefit of using a spray applied membrane was the freedom to work in and around other trades in limited windows, often being mobilised in more than one station.

Eptec also pressure injected chemical waterproofing material to many areas in the station caverns and running tunnels.

 