| End User/Client | ![]() |
||||||
| Sydney Water/Bovis-Tenix | |||||||
| Location | |||||||
|
Sydney, Australia |
|||||||
|
Description of works |
|||||||
| | Sewer rehabilitation of 900mm and 1200mm diameter steel pipes | ||||||
| | Abrasive blasting and epoxy lining of 500 lineal meters of pipe | ||||||
| Project Period | |||||||
| Oct 2000 - March 2001 | |||||||
| Project Details | |||||||
|
The work included epoxy lining, injection grouting of sewer leaks and repairs to corroded sewer sections. The project required the use of various chemicals ranging from epoxies, polyurethanes and cementitious products. This called for applicators with wide ranging experience in resin technologies, applying all materials.
|
![]() |
||||||