<< Back to Case History

End User/Client
 
  Rail Infrastructure Corporation
   
Location
  Sydney, Australia
 

Description of works

Lead based coating abatement
Recoating / corrosion protection
Negative pressure containment
24 hour track possession shutdown work    
     
Project Period    
  During 1998, 1999, 2000 and 2003
 
     
Project Details  
  Auburn 1998
  Westmead 1999
  Regent Park 1 1999
  Regent Park 2 1999
  Westmead 2 2000
  Potts Hill 2000
  Riverwood 2003
Macdonaldtown 2003
  Nepean 2005 - 2006
  Seven Hill 2007 - 2008
     

Project required undertaking the work during planned track possession with continuous round the clock operation to strict EPA constraints. The close proximity of the bridge structures to retail and residential areas made the planning and management of dust collection critical.

Bridges were scaffolded by conventional or suspended scaffold and encapsulated using specially selected reinforced translucent and flame retardant material.

The work required expertise in lead abatement and with particular attention to public relations, environmental and OHS&R issues.

The abrasive blasting was undertaken under a negative pressure environment created by high powered and efficient dust collection equipment.
 