<< Back to Case History

End User/Client
 
  Gerringong Sewerage Scheme
   
Location
  Wollongong, NSW, Australia
 

Description of works

Ground stabilisation
Resin injection
Consolidation of soils
Selection of materials
Manhole waterproofing
 
Project Period  
  2002      
     
Project Details  

The project required rehabilitation of new pipe that was damaged during installation and back filling operations.

The surrounding soil and gravel was highly permeable and had a water head of over 5m. Considering the depths and surrounding earth conditions, excavation was not a feasible option. Chemical Injection to suitable depths was undertaken to stabilise the soil. Subsequently the pipe was repaired by robotics from the inside, without ingress of water or soil, meanwhile preventing the possibility of collapse.

EPTEC;s simple innovative solution to the project proved to be cost and time effective.
 

 
<< back to case history | top