End User/Client
 
  RIO Tinto/Select Civil
   
Location
 

Wollongong, Australia

 

Description of works

Reinforcement cleaning and replacement
High pressure water blasting
Priming and coating concrete
Confined space procedures
Flow management
         
Project Period
  2002
   
Project Details

Works included removing spalled concrete that had left large areas of the steel reinforcement exposed.

EPTEC were awarded the work following development of repair solutions that met the Clients requirements. Costs and time for the project were minimised by selecting lightweight epoxy coatings combined with a corrosion protection system.

Safety management was a key consideration due to the potential for high flows in the culvert. EPTEC managed flow diversions and the confined space activities to provide a safe work environment.