| End User/Client | ![]() |
||||||
| Port Kembla Copper/ABB Engineering | |||||||
| Location | |||||||
|
Sydney, Australia |
|||||||
|
Description of works |
|||||||
| | FRP and PVC pipe work and FRP grating | ||||||
| | Design and scheduling for construction | ||||||
| | Preparation of isometrics | ||||||
| | Supervision of overseas manufacture, QA and delivery | ||||||
| | Site installation and management |
|
|||||
| Project Period | |||||||
| July 1998 - October 1999 | |||||||
| Project Details | |||||||
|
The challenge was to implement quality assurance procedures during the
overseas manufacture and ensure quality and time constrains were achieved.
The project was completed on time and to the Australian Standard quality
specifications of the client. |
|||||||
![]() |
|||||||